Morning at the Site
This morning we are working from the top to the bottom and pretty much everywhere in between. In the big picture below the first of the upper roof panels is being set into place while the concrete truck pours the basement slab.
Meanwhile, on the lower part of the roof we are running the electrical wires and wires for the security and alarm systems. We don’t want any exposed wiremold or electrical conduit so all ceiling mounted fixtures are being wired from the outside.
This requires careful planning and skilled hands. To the left Sam Joslin, of Century Electric, confers with Dave Vinick, of Home Electronics. To the right Len Capizanno locates the overhead fixtures.
And, while all this is going on up above, Ca-Gin Concrete pours the basement slab. The blue foam blocks mark the location of the footings for the steel columns that will support the floor and roof structure. Once the floor hardens the foam will be removed. And after the columns are set the diamond shapes will be patched and the concrete will secure the base of the columns.